Source: SEC EDGAR filings (8-K, 6-K, 10-Q exhibits) (U.S. Securities and Exchange Commission) · Public domain (U.S. government) · CSV

SEC EDGAR archives

idvaluegradeas of datepublished datetieraudited vs reportedextraction methodreview statusretrieved athttp statuscontent hashsupersedes idurlflags
8898175c4cb3fc1c$7.0Bgrade B, evidence tier 42025-06-022025-06-024company_statedmanualapproved2026-09-28 17:212009b596a785863—source page
Applied Digital -> CoreWeave two ~15-year data-centre leases, 250 MW at Polaris Forge 1 (signed 28 May 2025); 8-K splits it US$3B + US$4B. CoreWeave also got APLD warrants (buyer equity in seller, not counted).
abcb0df6b243926d$4.0Bgrade B, evidence tier 42025-08-292025-08-294company_statedmanualapproved2026-09-28 17:2120045623101dfbe—source page
Applied Digital -> CoreWeave third lease, 150 MW Building 4 at Polaris Forge 1 (signed 28 Aug 2025), ~15 years.
Raw snippets and dispute text
  • 8898175c4cb3fc1c has entered into two approximately 15-year lease agreements with CoreWeave, the AI Hyperscaler™. Under the lease agreements, Applied Digital will deliver 250 megawatts (MW) of critical IT load to host CoreWeave’s artificial intelligence (AI) and high-performance computing (HPC) infrastructure at its Ellendale, North Dakota data center campus. Over the approximately 15-year term, Applied Digital anticipates generating approximately $7 billion in total revenue from the leases.
  • abcb0df6b243926d This new lease agreement with CoreWeave brings Applied Digital’s total anticipated contracted lease revenue to approximately $11B, which includes $7B in revenue from the initial two approximately 15-year leases executed in May of this year.